EV Charger Installation: From Survey to Charging

A step-by-step look at a typical home EV charger installation

When Mark and Lisa in Altrincham ordered their new electric car, they knew they'd need a home charger. This case study follows their installation from initial enquiry to first charge, showing exactly what's involved in adding an EV charging point to your home.

EV charger installation
The completed installation ready for the new EV

Step 1: Initial Enquiry

Mark contacted us 6 weeks before his car was due for delivery. We discussed:

Step 2: Site Survey

We visited to assess the property and plan the installation:

We provided a fixed-price quote the same day.

Step 3: Preparation

Before installation day:

Step 4: Installation Day

The installation took approximately 4 hours:

  1. 8:30am: Arrived, confirmed plan with customer, set up work area
  2. 9:00am: Installed earth rod and tested
  3. 9:30am: Ran SWA cable from consumer unit through garage
  4. 11:00am: Mounted charger unit on external wall
  5. 11:30am: Made connections at both ends
  6. 12:00pm: Installed dedicated MCB and Type A RCD in consumer unit
  7. 12:30pm: Testing and commissioning

Step 5: Commissioning

With the physical installation complete:

Step 6: Documentation

We provided:

The Result

Mark and Lisa now have:

Customer Feedback

"The whole process was smooth and professional. They explained everything clearly, the installation was neat and tidy, and the charger works perfectly. We're saving a fortune charging overnight compared to public chargers." – Mark, Altrincham

Our EV charger installation service provides the same professional experience for all customers.

Conclusion

A home EV charger installation is straightforward when handled by experienced professionals. From survey to charging typically takes 1-2 weeks, and the installation itself is usually completed in half a day.